Harbor Logistics Park — Class A Distribution

1M+ sq ft Class A distribution facility delivered 11 weeks ahead of REIT's lease-up calendar.

11 weeks ahead
Schedule
Two tenants signed at substantial completion
Lease-up
Within 1% of baseline GMP
Cost
Challenge

The brief

Speculative build under inflationary pressure with tight utility easement and AQMD scrutiny.

Approach

How we ran it

  1. 01Early procurement of switchgear and dock equipment hedged 14% of cost inflation.
  2. 02AQMD strategy contracted before grading; zero plan-check cycles.
  3. 03Lean look-aheads and pull-planning gave back 11 weeks of float.
Outcome

What we delivered

Schedule
11 weeks ahead
Lease-up
Two tenants signed at substantial completion
Cost
Within 1% of baseline GMP